Voltane Research
Where power can be built near data centers
The analysis behind Voltane's Texas clean energy screening and its decision records: land and grid siting for solar, storage, wind and hybrid projects from public data and Voltane's screening models. Every number names its source.
- How Voltane estimates time to powerHow many months does a new grid connection in Texas take? Voltane estimates it from the public interconnection queue, group by group, and keeps every estimate apart from sourced facts.
- Time to power in PJM: what interconnection history showsHow long has a new grid connection taken in PJM, and how often did a request reach operation at all? The public queue history for Virginia, Ohio, Indiana and the rest of PJM, next to ERCOT, with a backtest.
- Texas has more than one gridMost of Texas runs on ERCOT, but not all of it. 32,055 of the sites Voltane screens sit on another grid, and that changes how to read them.
- How Voltane worksHow Texas screening becomes a sourced decision record: what goes into a match, what the match means, and what it cannot tell you.
- The coal-to-nuclear mapVoltane screens 407 former and retiring coal plant sites in 44 states as nuclear candidates. Here is where they are, how they match, and what separates a strong one from a weak one.
- Where Texas can still connectERCOT's interconnection queue holds 1,751 projects. Set county by county against the land Voltane finds, the pressure is very uneven.
- How Voltane scores real projectsWe took every US nuclear project with an NRC application since 2020 and looked up its site in Voltane: 8 sit on a candidate site, and 3 are not on our list at all.
Changelog: what changed in Voltane, and when
Screening by project type: solar · battery storage · data centers · ERCOT grid and land data · Texas counties · SB 6 cost calculator · For landowners
Need a site in ERCOT?
Tell Voltane what you need. We find candidate sites, report on each one's path to power and price it, with the source behind every number.