Texas SB 6 large-load cost calculator

What a large-load interconnection request in Texas costs up front under the adopted SB 6 rule: the security, the study fee, and what is kept if you withdraw.

Status of the rule: the Public Utility Commission of Texas adopted its large-load interconnection rule under Senate Bill 6 (16 TAC 25.194, Project 58481) on 2026-09-18. It took effect on 2026-10-08. The figures below are read from the adoption order, as of 2026-09-18.

Calculator

The same arithmetic for three request sizes. This table is computed when the page is built, so it reads the same with scripts off.

Requested peak demandSecurity to postStudy feeKept if withdrawn after capacity is allocated
100 MW$5,000,000$100,000$1,000,000
300 MW$15,000,000$100,000$3,000,000
1,000 MW$50,000,000$100,000$10,000,000

This is arithmetic on the published rule, not legal advice. Confirm with ERCOT and your transmission provider.

Where each figure comes from

FigureValueSourceAs of
Security per MW of requested peak demand$50,000PUCT Project 58481, order adopting 16 TAC 25.194 (d)(2)(B); adopted 2026-09-18, effective 2026-10-082026-09-18
Study fee (flat)$100,000PUCT Project 58481, order adopting 16 TAC 25.194 (d)(2)(A)2026-09-18
Share of the security kept on withdrawal after capacity is allocated20%PUCT Project 58481, order adopting 16 TAC 25.194 (d)(3)(B) to (E) and (f)(3)(B)2026-09-18
Large-load threshold75 MWPUCT Project 58481, order adopting 16 TAC 25.194 (b)(1)2026-09-18
Site control the rule acceptslease of at least five years, deed, or a signed option to purchase or leasePUCT Project 58481, order adopting 16 TAC 25.194 (d)(1)(A)2026-09-18

How to read them: the security is posted with the intermediate agreement, before the study. After the study it is the greater of that amount or the upgrade cost allocated to the request. The study fee is due when the intermediate agreement is signed, and the unused part is returned. ERCOT may add its own flat study fee, which the rule does not set. The kept share applies when a customer withdraws after ERCOT has allocated capacity, and the calculator assumes every requested MW was allocated. The whole security comes back, less amounts owed, on withdrawal before the study starts or when no capacity is allocated. All of it is forfeited when a customer neither withdraws nor signs the interconnection agreement by the deadline.

What SB 6 changed

Before the rule, a large new load in ERCOT could ask for a grid connection with little money down, and many requests covered the same project at several sites. The adopted rule applies to a new or expanded interconnection at or above the threshold (75 MW) at a single site. Before any study starts, the customer signs an intermediate agreement with the utility, shows site control, discloses duplicate requests elsewhere in Texas, pays the study fee and posts the security. The aim is that the requests ERCOT studies are backed by land and money.

What counts as site control

The rule accepts one of these property interests, held by the customer or an affiliate: lease of at least five years, deed, or a signed option to purchase or lease. A signed option counts, so a developer does not have to own the land before the study. Site control is shown before the study starts, and what a customer attests to is open to audit.

What the calculator leaves out

It does not estimate when power arrives. For that, read how Voltane estimates time to power. It also leaves out the cost of grid upgrades allocated after the study, any ERCOT study fee, payments in aid of construction, the price of the land, and the rules of utilities outside ERCOT. Use it to size the cash a request ties up, then check the current rule text.