How Voltane estimates time to power

How many months does a new grid connection in Texas take? Voltane estimates it from the public interconnection queue, group by group, and keeps every estimate apart from sourced facts.

Land near a line is only useful if power can reach it in time. So next to the facts about a Texas site, Voltane shows an estimate of how long a new grid connection is likely to take. This page says what is estimated, how, and how well the estimate held up against real projects.

What is estimated

Each estimate is a range, not a date: a low, a middle and a high value, taken from the lower quartile, the median and the upper quartile of past projects.

Estimates are made by group

Voltane does not model a single site's grid connection. It places the site in a group by its ERCOT zone, its voltage class and how crowded the interconnection queue is nearby, then reports what happened to past projects in that group. Every estimate names its group and the number of past projects behind it. A group with few past projects gives a weak estimate, and the count is shown so you can see that.

Facts and estimates are kept apart

Estimates are shown separately from sourced facts. A fact has a source and a date. An estimate is labelled "Estimate" and shows its range, its group and its method. The two never share a column.

The backtest

An estimate like this should be tested against what happened. We fitted the groups on older projects only, then compared what they predicted with newer projects the method had not seen. The result is printed here whether it flatters the method or not.

The backtest in short
MeasureResult
Projects in the test set135
Median error11.0 months
Actual results inside the predicted range57%
Fitted on projects through2019-12-31
Tested on projects from2020-01-01
Data as of2026-08-31
SourceBerkeley Lab "Queued Up" interconnection queue data file, 2026 edition (ERCOT requests through 2025-12-31, CC BY 4.0), compiled from ERCOT's monthly Generator Interconnection Status reports; ERCOT GIS report August 2026 (MIS report type 15933)

Median error is the typical gap, in months, between the predicted middle value and what happened. The predicted range runs from the low to the high estimate. Data (JSON)

Predicted against actual, by group
GroupTest projectsPredicted lowPredicted middlePredicted highActual middleActual inside the range
North zone4942.354.565.745.661%
South zone2945.560.171.147.255%
ERCOT-wide1739.052.266.449.071%
Coastal zone1046.953.667.445.440%
West zone1833.646.759.235.150%
West zone, 345 kV1234.048.960.540.450%

Months. Low, middle and high are the lower quartile, the median and the upper quartile. "Actual inside the range" is the share of the group's test projects that landed between the predicted low and high. Unknown means the file has no value. Data (JSON)

What this does not tell you

Use it in practice: Texas solar site selection · battery storage screening · reading ERCOT grid data

Screen Texas for your project

Voltane is Texas clean energy screening — solar, storage, wind and hybrid — that ends in a sourced decision record: the land, grid and permitting evidence, and the open questions, behind every site you consider.

Request a demoStart free