Worked example: backtesting time to power on public ERCOT data

A worked example on public data, not a client engagement. Client work is confidential.

The request

Every site search comes with the same question: how many months does a new grid connection in Texas take, and how far can that estimate be trusted? This example is the test Voltane ran on its own answer. The full write-up is How Voltane estimates time to power.

The estimate is a range, not a date: a low, a middle and a high value, taken from the lower quartile, the median and the upper quartile of past projects in the same group.

What the engine checked

The method is a hold-out by request year. Groups were fitted on ERCOT generation requests filed from 2015-01-01 to 2019-12-31, then compared with requests filed from 2020-01-01 to 2021-12-31 that the method had not seen. The queue history is as of 2026-08-31.

The data is the Berkeley Lab "Queued Up" interconnection queue data file, 2026 edition, compiled from ERCOT's monthly Generator Interconnection Status reports, plus the ERCOT GIS report of August 2026.

What came back

The test set held 135 projects. The median error was 11.0 months, and 57% of actual results fell inside the predicted range.

GroupTest projectsPredicted lowPredicted middlePredicted highActual middleActual inside the range
North zone4942.354.565.745.661.2%
South zone2945.560.171.147.255.2%
ERCOT-wide1739.052.266.449.070.6%
Coastal zone1046.953.667.445.440%
West zone1833.646.759.235.150%
West zone, 345 kV1234.048.960.540.450%

All values are months from an interconnection request to energization. In every group the actual middle came in under the predicted middle. That is not good news about speed. The test projects that could be counted are the ones that finished within 48 to 72 months, so the actual medians run short and will rise as slower projects finish.

The same method on PJM's public history, for comparison (Time to power in PJM):

MarketRequests in the fitted yearsReached operation, of those resolvedMonths to a signed agreement, middleMonths to power: low, middle, highBacktest median error
ERCOT (Texas)90745.1%22.438.8, 50.6, 62.311.0 months
PJM3,07415.9%37.826.9, 53.4, 70.614.0 months

The two clocks do not stop at the same point. ERCOT's figures use approval to energize or synchronize where the report lists one, else operation. PJM's use operation. Voltane's parcel screening is Texas today. PJM is planned, not live.

What stayed unknown

What a client would do next

Treat the range as a planning input, never as a date. In a Voltane report the estimate sits apart from sourced facts, is labelled "Estimate", and names its group, its range and the number of past projects behind it.

  1. Read the estimate against your target year, using the high value as well as the middle.
  2. Ask the utility or ERCOT for the study that actually sets a date. For a large load, that is the large-load process, which this history does not cover.
  3. Use the time to power definition when comparing estimates from different sources: where the clock starts and stops changes the number.

If you want this estimate attached to candidate sites for your own project, start at Find me a site. For a site you already hold, Analyze my site is available by request.

Questions people ask

How accurate was the ERCOT time to power backtest?

On 135 test projects the median error was 11.0 months, and 57% of actual results fell inside the predicted low-to-high range. The estimate also ran optimistic on the chance of energization within 48 months: 16.7% predicted against 14.4% actual.

Does the estimate apply to data centers?

Not directly. It is fitted on generation interconnection history: power plants and storage asking to connect. Large loads follow a different process, and no public site-level large-load history exists yet.

Is the estimate a date a utility has agreed to?

No. It says what happened to past projects in the same group. It is not available capacity, a queue position or an agreed date.

Sources