The sample
Each row is what one source states for one campus. Power is the planned figure at full build as the source words it, which may be grid capacity or IT load. Land is gross acreage: no source gives a density per buildable acre.
Texas pairs left out, and why
| Campus | Company | Place | MW | Acres | MW per acre | Why it is left out | Source |
|---|---|---|---|---|---|---|---|
| Lancaster campus | STACK Infrastructure | Lancaster (Dallas County) | 220 | 100 | 2.20 | the source says 'more than 100 acres', so the density is an upper bound | Denver’s STACK Infrastructure To Develop 100‑Acre, 220MW Data Center South of Dallas (Dallas Innovates) |
| Texas Critical Data Centers (TCDC) | New Era Energy & Digital | Ector County (outside Odessa) | 1,000 | 438 | 2.28 | an ambition of a developer with no tenant; an earlier report gave a quarter of the power | Firm Acquires Remainder of Data Center, Expands Campus (Permian Basin Oil and Gas Magazine, from the company release) |
| Grand Prairie campus | PowerHouse Data Centers / Provident Data Centers | Ellis County (just outside Grand Prairie) | 1,800 | 768 | 2.34 | the power figure is a switchyard rating, not an approved load | Dallas’ Provident Data Centers, Virginia’s PowerHouse Partner on ‘Hyperscale’ North Texas Campus (Dallas Innovates) |
| Project Horizon | Poolside (CoreWeave anchor tenant) | Pecos County area, West Texas | 2,000 | 568 | 3.52 | trade press quoting the company; unclear whether on-site generation sits inside the acreage | How CoreWeave and Poolside Are Teaming Up in West Texas to Build the Next Generation of AI Data Centers (Data Center Frontier) |
| Corsicana Facility | Riot Platforms (then Riot Blockchain) | Corsicana (Navarro County) | 1,000 | 265 | 3.77 | planned as a bitcoin mine, not a data center campus | Bitcoin Mining Company Investing $333M for New Facility South of Dallas (Dallas Innovates) |
With these left in, the median of 17 Texas pairs is 1.64 MW per acre. Voltane uses the lower figure.
Not comparable
| Campus | Company | Place | MW | Acres | MW per acre | Why it is left out | Source |
|---|---|---|---|---|---|---|---|
| River Bend | Hut 8 | West Feliciana Parish, LA | 330 | 627 | 0.53 | outside Texas | River Bend | Hut 8 (company site page) |
| Homer City Energy Campus | Homer City Redevelopment | Homer City (Indiana County), PA | 4,500 | 3,200 | 1.41 | outside Texas | Pennsylvania to host largest-ever US gas plant to fuel data centers (E&E News) |
| Project Matador (HyperGrid campus) | Fermi America | Carson County (near Amarillo) | 11,000 | 5,769 | 1.91 | the power figure is generation, not a campus load at full build | Rick Perry-led company plans to build nation’s largest AI, nuclear project (E&E News) |
| Lighthouse (Stargate Port Washington) | Vantage Data Centers (OpenAI / Oracle) | Port Washington (Ozaukee County), WI | 1,300 | 672 | 1.93 | outside Texas | Construction Team Chosen for First Phase of $15B Wisconsin Data Center Campus (Engineering News-Record) |
| Stargate Michigan (Saline Township) | Related Digital (OpenAI / Oracle) | Saline Township (Washtenaw County), MI | 1,400 | 575 | 2.43 | outside Texas | Tech giants announce $7B data center, Michigan’s first hyperscale campus (Bridge Michigan) |
How Voltane uses the figure
- A site's data center load is its buildable acres, capped at one campus of 500 acres, times 1.33 MW per acre.
- The sources give gross acres. Buildable acres are fewer, so applying the figure to buildable acres gives the lower reading.
- It is land-based sizing. It is not grid capacity and not a load any utility has agreed to serve.
- On a Site Price Sheet the figure is printed with this sample as its source, and you can replace it with your own.
Questions people ask
How many megawatts per acre does a data center campus need?
Announced Texas campuses state between 0.68 and 3.7 MW per gross acre at full build, with a median of 1.33. The spread is wide because campuses differ in cooling, buffers and on-site power.
Is this per buildable acre?
No. Every source gives gross campus acreage. No public source in the sample states a density per buildable acre.
Why are some campuses left out?
A pair is left out when the power figure is not a campus load, such as a switchyard rating or on-site generation, or when the land figure is only a bound. Each one is listed with its reason.
Related
- Find me a site
- Analyze my site (by request)
- Texas data center projects: what the public record shows
- How to price a powered land site
- The data behind a data center site report
More guides
- How to find a data center site in Texas
- The ERCOT large load interconnection process, explained
- What makes land "powered land"?
- Data center site selection checklist: power, land, water, fiber, risk
- How to price a powered land site
- Time to power: what drives it in ERCOT
- Gas-to-power and behind-the-meter generation for data centers: siting basics
- Solar and storage site selection in Texas: a first-pass screen
Need a site, or have one?
Tell us what you need and Voltane finds, reports on and prices candidate sites for your project, in any market. Or bring a site you already have for a path-to-power report.